If 3 men and 4 boys complete a work in 7 days and 2 men and 3 boys do the same work in 10 days . In
Prakash Joshi
If 3 men and 4 boys complete a work in 7 days and 2 men and 3 boys do the same work in 10 days . In how many days will 3 men and 8 boys complete the same work.